8 workers can finish a project in 15 days. How many workers are needed to finish it in 10 days at the same rate?

Correct answer: D. 12

The project needs 8 × 15 = 120 worker-days. To finish in 10 days: 120 ÷ 10 = 12 workers. Fewer days require more workers, so this is inverse variation.

medium

Answer and explanation

The correct answer is D. 12

The project needs 8 × 15 = 120 worker-days. To finish in 10 days: 120 ÷ 10 = 12 workers. Fewer days require more workers, so this is inverse variation.

Topic: Work and Motion Problems MCQs · Subject: Numerical Ability